PROGRESS REPORT OF PROJECTS UNDER KNNL AS ON 31.03.2007.

Click here for the progress report in Kannada

Sl. No. Particulars Progress as on 31.03.2007
1. Ghataprabha Project  
  (1) Dam works Completed.
  (2) GLBC (109 Km.) Completed.
  (3) GRBC (199.093 Km.) Length completed upto Km.119 (except lining works in Km.82, 83, 92 & 110). Water let out for irrigation upto Km. 119. Works are completed from Km. 128 to 130, 132, 136 and 138 to 145, 147 to 186, 188 to 190, 195 & 196 Km. In Km.120-121, 123-124 and 125-126, fresh agencies for the balance work has been fixed, the works are nearing completion. In km 135, agency stopped the work and contract has been rescinded and fresh tenders for balance work has been invited. In the remaining reaches, works are under various stages of progress upto km 199.093. There is a major aqueduct in km 160 and the work is completed.
  (4) Distributories under GRBC (37 nos.) Works of distributory blocks 1 to 30 and block No.33 are completed and works in distributory blocks 31,32,34,35,36 & 37 are under various stages of progress.
  (5) Chikkodi Branch Canal (88 Km.) Works completed to its full length of 88 Kms and water let out for irrigation.
  (6) Distributories under CBC (25 nos.) Works completed in all Blocks except Block no. 21. Under block No.21, works completed upto km 15 and works are under progress from km 16 to 29. Km 30 to 35, estimates have been prepared and for further reaches survey works are under progress.
2. Malaprabha Project  
  (1) Dam works Completed.
  (2) MRBC (142 Km.) Length completed upto Km. 131. From Km. 131 to 142 works are under progress. Water let out upto 130 km.
  (3) MLBC (150 Km.) Length completed upto Km.150. Water let out upto 140 Km.
  (4) Distributories under MRBC (60 nos.) Works completed in block nos.1 to 52, 53A, 53B, 54, 55, & 56A. Works in block nos. 56B, 56C, 57, 58, 59 & 60 are under progress. Tenders have been invited for Dy.No.59D in block No.59.
  (5) Distributories under MLBC (58 nos.) Works completed upto block no.1 to 57A. Works are under progress in 58 th block.
3. Hippargi Project  
  (1) Barrage works Barrage works completed. Fabrication and erection of crest gates works completed. Water is being stored in the reservoir.
  (2) L.I. Systems : Head works The works for the lifting systems of two foreshore LI schemes, namely Halyal and Ainapur on turnkey basis are entrusted. The works of Ainapur lifting system and Halyal Stage-II are nearing completion and the works of Halyal stage-I are under progress. Works of Karimasuthi 3 rd stage and Savalgi-Tungal 4 th stage under Halyal LIS are under progress.
  (3) Canals The work of combined canal of Ainapur LIS and Upto Km. 10 of Ainapur east canal, works are under progress. Agency fixed from Km. 1 to 10 of Ainapur west canal, from Km. 1 to 5 & Km.11 to 35 of Halyal east canal, from Km.1 to 10 of Halyal west canal and from Km.0 to 7.42 of Savalgi-Tungal west canal and works are under progress. The agency fixed from Km.10 to 27.52 & Km.36 to 40 of Halyal east canal. Tenders are invited from Km.0 to 10 of Savalgi-Tungal east canal, from Km.0 to 20 of Karimasuthi east canal including combined canal of Karimasuthi LIS . In the balance reaches under Ainapur & Halyal LIS survey works, approval to general alignment, design and preparation of estimates are under progress. Survey works, preparation of general alignment of Karimasuthi & Savalgi-Tungal east & west canal are under progress.
4. Markandeya Project  
  (1) Dam works Canals The concreting work of dam is completed. Spillway bridge and fabrication of 6 crest gates are completed. Construction of parapet is completed and electrification work is under progress.
  (2) RBC (71 Kms.) Works are completed from Km.1 to 71. Water is let out on trial run upto km 65.
  (3) Distributory under MRBC (45 Nos.) Distributory works in blocks no.1 to 11, 14 to 45 are completed & in the balance blocks, works are under progress.
  (4) LBC (15 Kms.) Works are completed from Km.7 to 15. Works are under progress from Km.1 to 6.
5. Harinala Project  
  (1) Dam works Dam work completed.
  (2) Canal works (a) R.B.C. (10.50 Km) (b) L.B.C. (8.5 Km.) Works completed. Works completed.
6. Upper Tunga Project  
  (1) Dam works Dam work including spillway bridge work, parapet is completed. Electrification works and erection of crest gate works are completed.
  (2) Main Canals (339 Kms.) Main Canal works upto km 168.50 are under progress. Tunnel from km 168.5 to 174, km is progress. Out of 4000m of tunnel proper 3985mt length is excavated and lining of tunnel is also under progress. Lining works of main canal is under progress. Main canal work from km.175 onwards upto km.192 is under progress. For further reaches survey preparation of estimates is under progress.
  (3) Distributory canal: Work of Dy. No.1 & 2 are nearing completion. Main canal sluice work and minor and sub minor works are also in progress.
7. Singatalur Project  
  (1) Barrage Barrage works are in progress.
  (2) Head works 1 st stage lifting arrangements on R/S of SLIS, work is in progress.
  (3) Canal works on right sides Balance works of Rajwal & Ayyanhally branch canal are nearing completion. Left side intake canal work is also in progress.
     
8. Bhima Lift Irrigation Scheme  
  (1) Barrage works Earthen embankment works are completed. Construction of barrage is under progress.
  (2) L.I Works The lifting system works for Balundagi & Allagi lift are under progress.
  (3) Crest gate works The crest gate work is entrusted to M/s. KSCC and the fabrication & erection work is under progress.
  (4) Canal works a) Construction of Balundagi main canal from 0 to 25 km works is under progress. Tender process is under progress for construction of canal from Km.26 to 45. b) Construction of Allagi main canal from 0 to 20 km is under progress. Tenders were invited for construction of 20 to 35 km of Allagi main canal.
9. Gandorinala Project  
  (1) Dam works Dam & crest gates works are completed.
  (2) Canal works a) R.B.C (7Km.) b) L.B.C. (94 Km) R.B.C. works up to 7 Kms. completed. From km 20 to 27, nearing completion. From Km.28 to 90 km works are under progress.
10. Tunga Lift Irrigation Scheme The estimate of this project is approved for Rs.21.42 crores. The work could not be started since this project comes within Shettihalli Wild Life Sanctuary area. Permission to divert Wildlife Sanctuary lands requires approval of Hon'ble Supreme Court. Forest Department has already been approached in this matter seeking relevant permission. As per the suggestions of the Forest Department, possibility of alternative routes for implementing the scheme outside the forest area is being verified.
11. Kalasa Nala & Bandur Nala diversion Schemes : To tackle dam works The proposal for taking up of the diversion works of Kalasa Nala & Bandur Nala Projects in non forest is commenced.
12. Dudhganga project This is an Inter-State project. The dam situated in Maharastra state & construction of the Dam is already completed.
  •  Nidhori branch canal (25Kms.) (Entry into Karnataka Border at 25 th km.) NBC Works are completed from Km.25 to 47 km. The works in km.48 to 50 are under progress. All distributory blocks are completed. Tenders are invited for FIC's works.
  •  Bidri branch canal (49 Kms.) (Entry into Karnataka Border at 44 th km.) The works are under progress from Km.44 to 49, 54 to 62. From km.50 to 53 the works has to be tendered. Estimates are under preparation from km.63 to 65.
  (3) Kurundawad branch canal (9Kms) To be executed by Maharashtra State .
  (4) Dattawad branch canal (30Kms.) Dattawad link canal from Ch.0+000 km to Ch.0+700 km. Agency fixed and agreement to be executed by the agency. Dattawad RBC and LBC works are under progress.
13. Basapur LIS   Out of 1 st stage works, head works are partially completed procurement of pumping machinery are in progress. The construction of canal is in progress. Power required for this scheme is approved by HESCOM and necessary deposits are to be made to HESCOM. Tender invited for 2 nd stage works.
14. Itagi-Sasalwad LIS Concrete work for jack well / pump house is in progress. Out of 237 pipes required for raising main, all pipes are already laid. The contractor has procured all the 4 pumps and motors required for this project. The total length of right bank canal is 25.517 km, out of this the work for first 8.77 km and left bank canal 10.907 kms works are physically completed. Balance works of right bank canal i.e. from kmn.8.77 to km.25.517 are in progress and nearing completion. Works are under progress in distributory and minors of right bank and left bank canal. Getting power connection from HESCOM for this project is in progress.
15. Bennithora  
  (1) Earthern Dam Completed.
  (2) Right Bank Canal – 82 KM Works are completed.
  (3) Left Bank Canal – 60 KM Works are completed.
  (4) Distributaries under RBC – 39 Nos. 39 distributory works are completed.
  (5) Distributaries under LBC – 30 Nos. 23 distributory works are completed, 7 are in progress.
16. Lower Mullamari Project  
  (1) Earthern Dam Completed. Spillway works are completed.
  (2) Right Bank Canal – 80 Kms. Works are completed.
  (3) Distributaries – 66 Nos. 64 distributories are completed, 2 are in progress and nearing completion.
17. Varahi Project  
  (1) Diversion weir works Work is under progress.
  (2) Right Bank Canal (46.80 Km) River aqueduct works are under progress. Survey works completed. Upto 8.40 km (including tunnel) agencies fixed. From km.9 to 14 estimates are under approval stage. In the remaining reaches, estimates are under preparation.
  (3) Left Bank Canal (44.32 Km) Upto 21 km works are in various stages of progress. Agency fixed for major aqueducts at Km.9, 11, 12 & 13 of VLBC & works are under progress.
  (4) Lift irrigation canal (33 Km) Head works are completed. Power connection received and commissioned on trial basis.
18. Amarja Project  
  (1) Dam works Works completed, water being stored.
  (2) Right Bank Canal (45 KM) Partially completed. Rectification and balance work upto 20 Km is under progress. Agency fixed for rectification and balance work from km 20.00 to km.42.48.
  (3) Left Bank Canal (55 km) Partially completed. Tender invited for first 30 km rectification & balance work.
  (4) Distributaries Partially completed, FIC works are to be started. Survey for balance works is under progress.
19. Hiyranyakeshi LIS Works are under progress.
20. Bennihalla LIS
21. Kolachi LIS
22. Konnur LIS
23. Sri Rameshwara LIS
24. Javalu halla LIS
25. Umbrani Amruthapura LIS Umbrani Amruthapura LIS stage-I is under progress. Out of 14km of raising main 10km laying and joining of pipeline is completed. In take jackwell of pump house, raft concrete is completed. Further fabrication & centering of side walls is under progress. Forest land trees cutting is completed. Umbrani Amruthapura LIS stage-II tenders are received and process of finalisation of agency is in progress.
26. Guddada Mallapura LIS Earthwork excavation for jackwell / pump house is completed and concreting is in progress. 2 delivery chambers are completed. Earth work excavation for 1 st stage raising main is completed. Earth work for 2 nd stage raising main, gravity canal-1 is completed. Work for UG sump completed. Excavation for gravity canal-II, III are in progress.
27. Bellary Nala Project Excavation for dam foundation, concreting in block No.1 to 6 and 9 to 16 are under progress. C-Planning is approved and alignment from km 1 to 20 is also approved. Survey work for remaining canal networks are under progress.
28. Upper Bhadra Stage-I Process for implementing the project is in progress.

Note: In general, the progress in Projects implementation is satisfactory.

 

 

 

Date: 9.5.2007 ( D. SATYA MURTY)

Place: Bangalore MANAGING DIRECTOR