Projects:

12.BANDURA NALA

These two Projects  envisage diversion of  7.56 TMC of water to Malaprabha Dam by constructing dam across the above nalas and diversion canals.
Administrative approval for these two projects accorded by Government in May 2000.
Environmental clearance obtained from State Government.
Proposal for diversion of about 500 ha. submitted to MOEF, GOI by State Government and the matter is being pursued.
Survey, design etc., of the above two projects entrusted to     KPCL. The designs, estimates and DTP for Kalasa dam are under finalisation.
Designs, estimates for Bandur nala diversion schemes are under preparation.
Interstate meeting of Secretaries of Goa, Karnataka and Maharashtra, convened by CWC was held in May 2001.
Hydrological study for assessment of yield of Madei/Mandovi river will be carried out by CWC in consultation with Goa, Karnataka and Maharashtra.
The report on the above expected to be submitted within three months.

WATER ALLOCATION AND ULTIMATE POTENTIAL OF THE PROJECTS

Sl No

Project

Allocation (TMC)

Ultimate Potential (In Ha)

1

Ghataprabha

79.00

3,31,000

2

Malaprabha

44.53

2,20,028

3

Hippargi

12.56

50,587

4

Markandeya

4.00

19,105

5

Harinala

0.80

3,480

6

Singatalur

7.64

20,241

7

Bhima Lift

6.00

24,292

8

Upper Tunga Project

12.24

94,698

9

Gandorinala

2.16

8,094

10

Tunga Lift

1.43

1,708

11

Kalasa Nala

3.56

-

12

Bandura Nala

4.00

-


Previous Project Estimated Cost & Physical Programme

 

Back to Top

 

 


 