Projects:

9. GANDORINALA

The project comprises an earthen dam across Gandorinala near Belkota      village in Gulbarga district to irrigate 8,094 Ha.
ØDam & allied works
Earthen dam work completed, except filling of gorge portion for which tenders are invited.
Spillway concreting works in progress over 95 % concreting completed.
The work of supply and erection of radial crest gates awarded to M/s. TSP Ltd., on tender basis and same is in advance stage of progress.
ØR&R master plan prepared and works in rehabilitation centers under progress.
ØCanal works
Right Bank Canal work of 7 Kms under progress.
Out of 94 Km of left bank canal tenders under finalisation  for Km. 0 to 5 and tenders accepted for Km. 5 to 20.
Estimates under preparation for Km 21 to 40.
Surveys under progress for Km. 41 to 94.
Survey work of distributory network completed and preparation of estimates being taken up.

Previous Project Back to Projects Next Project

 

Back to Top

 

 


 

E-mail: