KARNATAKA
NEERAVARI NIGAM LIMITED
(A Government of Karnataka Undertaking)
|
|
Regd. Office
: 4th Floor, Coffee Board Building,
|
|
No. 1, Dr. B.r.
Ambedkar Veedhi, Bangalore - 560 001
.Ph : 080- 2283074 - 78 Fax : 080 - 2267314
|
CONTENTS

|
|

|
|
BRIEF
TENDER NOTIFICATION
|
Go
to Top
|
| |
|
|
KARNATAKA
NEERAVARI NIGAM LIMITED
(A Government of Karnataka Enterprise)
Office of the Executive Engineer, KNNL, SLI Division, Mundangiri.
No: EE/KNNL/SLID/TS/TND/2001-02/82
|
|
|
TENDER
NOTIFICATION
|
|
|
(1) Sealed item rate tenders
in duplicate duly superscribing the name of work are invited
by the Executive Engineer, KNNL, SLI
Division, Mundargi, from the Contractors enrolled in
the select List of contractors under Category-ll and
above by KNNL, on behalf of the Managing Director, Karnataka
Neeravari Nigam Ltd., Bangalore.
|
|
(2)
The details of works put to tender :
|
SI.
No.
|
Name
of work
|
Approximate
amount put
to tender
(Rs. in lakhs)
|
E.M.D.
(Rs. in lakhs)
|
Stipulated
period
of completion
(including
monsoon)
|
|
1.
|
Package
I : Construction of intake Channel
on Left Bank of SLIS for 1st
& 2nd Km
(including C.D. works) and construction of flood
protection bund.
|
1136.00
|
11.36
|
12
Months
|
|
2.
|
Package
II : Construction of intake Channel
on Left Bank of SLIS for 3rd
& 4th Km
(including
C.D. works).
|
614.68
|
6.15
|
12
Months
|
|
3.
|
Package
III : Construction of intake Channel on Left
Bank of SLIS for 5th to 7th Km
(including
C.D. works).
|
584.77
|
5.85
|
12
Months
|
|
|
|
(3) The
last date for receipt of application for tender
document is on 31stAugust
2001 upto 5.30
p.m. The cost of Blank Tender Booklets per package including
KST and surcharge is Rs. 15,000/-
(Rupees Fifteen thousand only). It
is non - refundable and shall be in the form of
crossed Demand Draft of Bankers Cheque of a Scheduled
Bank drawn in favour of KNNL, SLI Division, Mundargi payable at
Mundargi and shall be attached with the application.
(4)
The tender documents will be issued
on 26th and 27th September 2001
on production of copy of
valid enrolment certificate.
Applications will be
received, blank tender documents will
be issued and completed
tender
documents will be received in the
following offices : (i) Registered
office of
KNNL, 4th Floor,
Coffee Board Building, Dr.
B. R. Ambedkar Veedhi, Bangalore-560 001. (ii)
Office of the Chief Engineer, Irrigation Central Zone,
Munirabad-583 233. (iii)
Office
of the Executive Engineer, KNNL, SLI Division,
Mundargi-582 118.
(5) The completed
bid documents duly superscribed with the name of work
shall
be received at any of the above
mentioned office from 15th
to 17th October
2001 between 11.00 a.m. and 4.00 p.m.
The tender documents will be
opened on 20th October 2001 at 11.00 a.m. or any other
convenient day in
presence of the tenderers or their representatives by the Executive
Engineer, KNNL, SLI
Division, Mundargi
in his office.
(6) This office will not be
responsible for any postal delay.
(7) The KNNL reserves
the right of rejecting any or all tenders without
assigning
any reasons. The successful bidder shall
have to produce an additional Bank
Guarantee for the difference Amount below
25% if quoted rates are below
25% of estimated rates,
before executing the Agreement
with KNNL.
(8) The total cost
of work on hand in KNNL with one contractor should not Exceed
Rs. 20 crores (Rupees Twenty crores only)
and this would be excluding any
major works Like Dam / Lift Irrigation ect., of specialised
nature. The contractor
should enclose a statement showing lists of works on
hand in KNNL alongwith
amount put to tender in the tender document.
(9) In case, there
is any part or whole land required for the work is not
acquired by the KNNL, It shall be the
full responsibility of the contractor to
procure
possession of such
lands by consent of
the land owners before commencement
of the work at no extra cost to KNNL.
(10) Any additional Information/Clarifications
may be obtained from the office of the undersigned during office
hours On
working days.
Sd/-
Executive Engineer, KNNL, SLI Division, Mundargi.
|
|
| |
|
|
KARNATAKA
NEERAVARI NIGAM LIMITED
(A Government of Karnataka Enterprise)
Office of the Executive Engineer, KNNL, SLI Division, Mundangiri.
No: EE/KNNL/SLID/TS/TND/2001-02/82
|
|
|
TENDER
NOTIFICATION
|
|
|
(1) Sealed item
rate tenders in duplicate duly superscribing the name of work are
invited by the Executive Engineer,
KNNL, SLI Division, Mundargi, from the Contractors enrolled
in the select list of contractors under Category-l by KNNL, on behalf
of the Managing Director, Karnataka Neeravari Nigam Ltd.,Bangalore.
|
|
(2)
The
details of works put to tender :
|
SI.
No.
|
Name
of work
|
Approximate
amount put
to tender
(Rs. in Crores)
|
E.M.D.
(Rs. in lakhs)
|
Stipulated
period
of completion
(including
monsoon)
|
|
1.
|
Construction of balance works
of Barrage for Singatalur Lift
Irrigation near Hammigi Village,
Mundargi Taluk.
|
25.27
|
25.27
|
24
Months
|
|
|
|
(3) The last date
for receipt of application for tender document is on 28th
August
2001
upto 5.30 p.m. The
cost of Blank Tender Booklets per set including
KST and surcharge is Rs . 15,000/-
(Rupees Fifteen thousand only). It is
non - refundable and shall be in the form of crossed Demand
Draft or Bankers
Cheque of a Scheduled Bank drawn in favour of KNNL, SLI
Division, Mundargi
payable at Mundargi and shall be attached with the application.
(4)
The tender documents will be issued on 20th and 21st September 2001
on
production of copy of valid enrolment certificate.
Application will be received,
blank tender documents will be issued and completed
tender documents will
be received in the following offices
: (i) Registered office
of KNNL, 4th Floor,
Coffee Board Building, Dr. B.R.
Ambedkar Veedhi, Bangalore - 5600 01.
(ii) Office of the Chief Engineer,
Irrigation Central Zone, Munirabad-583 233.
(iii)
Office of the Executive Engineer, KNNL
SLI Division, Mundargi-582 118.
(5)
The completed bid documents duly superscribed
with the name of work shall be
received at any of the above mentioned offices
from 8th
to 10th October 2001
between 11.00 a.m. and 4.00 p.m. The tender documents
will be opened on 12th October 2001 at 11.00 a.m.
or any other convenient day in presence
of
the tenderers or their representatives by the Executive
Engineer, KNNL, SLI
Division, Mundargi in his office.
(6)
This office will not be responsible for any postal delay.
(7)
The KNNL reserves the right of rejecting of any
or all tenders without assigning
any reasons. The successful
bidder shall have to produce an additional Bank
Guarantee for the difference amount
below 25%, if quoted rates are below 25%
of estimated rates, before executing the agreement
with KNNL.
(8)
The total
cost of work on hand in KNNL with one contractor should not
exceed Rs. 20 Crores (Rupees Twenty
crores only) and this would be excluding any
major works like Dam / Lift Irrigation etc., of specialised
nature. The contractor
should enclose a statement showing
lists of works on hand in KNNL alongwith
amount put to tender in the tender document.
(9)
Any additional information / clarifications
may be obtained from the office the
undersigned during
office hours on working days.
Sd/-
Executive Engineer, KNNL, SLI Division, Mundargi.
|
|
| |
|
|
KARNATAKA
NEERAVARI NIGAM LIMITED
(A Government of Karnataka Enterprise)
Office of the Executive Engineer, KNNL, SLI Division, Mundangiri-582
118
No: EE/KNNL/SLID/TS/TND/2001-02/90
|
|
| |
|
|
TENDER
NOTIFICATION
|
Go
to Top
|
|
(1)
Sealed tender in duplicate duly superscribing the name of
work are invited on turnkey
basis by the Executive Engineer, KNNL, SLI Division, Mundargi,
from the Contractors pre-qualified for taking up Lift Irrigation
Works on turnkey basis under KNNL, on behalf of the Managing Director,
Karnataka
Neeravari Nigam Ltd., Bangalore.
|
|
(2)
The details of works put to tender:
| Name
of work |
Approximate
amount put
to tender
(Rs. in Crores) |
E.M.D.
(Rs. in lakhs) |
Stipulated
period
of completion
(including
monsoon) |
Category
of eligible
Contractors |
|
Package
I: Design, Supply, Installation,
Testing and Commissioning of Lift Irrigation Systems
for 1st stage on Right Bank Canal of Singatalur
Barrage on Turnkey basis consisting
of following: Jackwell-cum-Pump House, including
Intake Arrangement, Pumping
Machineries, Rising
Mains, Substation Works and
Pump House, Electrical Works,
Supply of Spare Parts, Tools including
Operation of Systems for 2 years
beyond the date of
completion. Total
|
10.20
|
10.20
|
24 Months
|
I & II
|
|
Package
II : Design, Supply, Installation, Testing
and Commissioning of Lift Irrigation Systems for 1st
Stage on Left Bank Canal of singatalur Barrage
on Turnkey basis consisting
of following: Jackwell-cum-Pump House, including
Intake Arrangement, Delivery Chamber,
Pumping Machineries, Rising
Mains, Substation Works
and Pump House, Electrical
Works, Supply of Spare Parts, Tools including
operation of System for 2 years
Beyond
the date of completions. Total
|
26.35
|
26.35
|
24 Months
|
I
|
|
Package
III: Design, Supply, Installation, Testing
and Commissioning of Lift Irrigation Systems for
2nd Stage on Left Bank Canal of Singatalur Barrage
on Turnkey basis consisting
of following: Jackwell-cum-Pump House, including
Intake Arrangement, Delivery Chamber,
Pumping Machineries, Rising Mains,
Substation Works & Pump House, Electrical
Works, Supply of Spare
Parts, Tools including operation of
System for 2 years Beyond
the date of completions. Total
|
29.00
|
29.00
|
24 Months
|
I
|
|
Package
IV: Design,
Supply, Installation, Testing and Commissioning of Lift
Irrigation Systems for 3rd Stage on Left Bank
Canal of Singatalur Barrage on
Turnkey basis consisting of following: Jackwell-cum-Pump
House, including Intake
Arrangement, Delivery Chamber, Pumping
Machineries, Rising Mains, Substation Works
& Pump House, Electrical Works, Supply
of Spare Parts, Tools including Operation of System
for 2 years Beyond
the date of completions. Total
|
37.75
|
37.75
|
24 Months
|
I
|
|
|
|
(3)
The last date for receipt of application
for tender document is on 23rd
August
2001 upto 5.30
p.m. The cost of Blank Tender Booklets per set
including KST
and surcharge is Rs . 15,000/-
(Rupees Fifteen thousand only). It
is
non-refundable and shall be in
the form of crossed Demand Draft drawn in
favour of Executive
Engineer, KNNL, SLI Division,
Mundargi payable
at Mundargi and shall be attached with the application.
|
|
|
(4) The tender
documents will be issued on 3rd
and 4th September 2001 on
production of copy of
valid enrolment certificate. Applications will be received,
blank tender documents will be issued
and completed tender documents will be
received in the following offices:
(i)
Registered office of KNNL, 4th Floor, Coffee
Board Building, Dr. B.R. Ambedkar
Veedhi, Bangalore-560 001. (ii)
Office of the
Chief Engineer, Irrigation
Central Zone, Munirabad -583 233. (iii)
Office of the
Executive Engineer, KNNL,
SLI Division, Mundargi-582 118.
|
|
|
(5)
A pre-bid conference will be held on 24th
September 2001.
|
|
|
(6)
The completed bids shall be received at any of the above
mentioned offices from
15th
to 17th October 2001 between
11.00 a.m. and 4.00 p.m. The tender
documents will be opened on
19th
October 2001 at 11.00 a.m. or any other
convenient day in the presence
of the tenderers
or their representatives by the
Executive Engineer, KNNL, SLI Division, Mundargi.
|
|
| (7)
This
office will not be responsible for any postal delays.
|
|
|
(8)
The KNNL reserves the right of rejecting any or all tenders
without assigning any
reasons. The successful bidder
shall have to produce an additional
Bank
Guarantee for the difference amount below 25%
if quoted rates are below 25% of
estimated rates, before executing the agreement
with KNNL.
|
|
|
(9)
Any additional information / clarifications may be obtained
from the office of the
undersigned during office hours on working days.
|
|
|
Sd/-
(V.P. UPPIHAL) Executive
Engineer, KNNL, SLI Division, Mundargi.
|
|
| |
|
|
|
|
NO-KNNL/MBC/DN-1/PB-3/TND-2/2001-02-933
|
|
|
Office
of the
Executive Engineer
KNNL, MBC Divn No-1
Gaddanakeri-587102
Dtd:
23/08/2001
|
|
|
TENDER-NOTIFICATION
|
|
|
Sealed
item rate in duplicate are invited by the undersigned on behalf
of Managing Director Karnataka Neeravari Nigam
Limited from contractors registered with
K.P.W.D. and enrolled in the select list of contractors of KNNL
under appropriate category for the works mentioned in the
statement below.
|
|
| |
|
|
The
blank tender documents will be issued and the completed tender documents
will be received at any of the following offices
.
1)
Office of the Executive Engineer, MBC Division
No-1 Gaddanakeri.
Tq & Dist.Bagalkot.
2)
Office of the Chief Engineer,
KNNL Irrigation (North) Belgaum
3) Managing
Director, KNNL
4th floor, Coffee Board
Building,
Dr. Ambedkar Veedhi, Bangalore
-1.
|
|
| Details
of works put to tender and category of contractors eligible to tender.
|
|
|
Sl
No.
|
Name
of the work
|
Package
No.
|
Approx.
Amount put to tender Rs. In lakhs
|
E.M.D.
Rs. In Lakhs
|
Category
Enrolled under KNNL
select list of contractors
|
Stipulated
period of completion (including mansoon)
|
|
01
|
02
|
03
|
04
|
05
|
06
|
07
|
|
1)
|
Construction
of GRBC Km No.151 to 153 earth work and lining
|
I
|
604.39
|
6.04
|
II
& above
|
12
months
|
|
2)
|
Construction
of GRBC Km No. 154 to 156 earth work, lining and CD works
|
II
|
526.25
|
5.26
|
-do-
|
12
months
|
|
3)
|
Construction
of GRBC Km No. 157 to 159 earth work and lining
|
III
|
520.78
|
5.21
|
-do-
|
12
months
|
|
4)
|
Construction
of GRBC Km No. 160 to 162 earth work, lining and CD works
|
IV
|
338.05
|
3.38
|
III
& above
|
12
months
|
|
5)
|
Construction
of GRBC Km No. 163 earth work, lining and CD works
|
V
|
795.45
|
7.95
|
II
& above
|
12
months
|
|
6)
|
Construction
of GRBC Km No. 164 to 165 earth work and lining
|
VI
|
249.79
|
2.50
|
III
& above
|
09
months
|
|
7)
|
Construction
of GRBC Km No. 166 to 167 earth work, lining and CD works
|
VII
|
506.17
|
5.07
|
II
& above
|
12
months
|
|
8)
|
Construction
of GRBC Km No. 168 earth work, lining and CD works
|
VIII
|
363.46
|
3.46
|
III
& above
|
12
months
|
|
9)
|
Construction
of GRBC Km No. 169 to 170 earth work, lining and CD works
|
IX
|
268.36
|
2.68
|
-do-
|
09
months
|
|
10)
|
Construction
of GRBC Km No. 171 to 175 earth work, lining and CD works
|
X
|
243.04
|
2.43
|
-do-
|
09
months
|
|
11)
|
Construction
of GRBC Km No. 176 to 180 earth work, lining and CD works
|
XI
|
246.99
|
2.47
|
-do-
|
| | |